Protection Engineering Power Systems IEC 60255  ·  IEC 60909  ·  CEA Safety Regulations 2023  ·  IEEE 1584-2018

What Is Relay Coordination
and Why Is It Required?

An uncoordinated protection system cannot guarantee that only the faulted section is isolated. This is what industrial facilities need to understand about relay coordination — and the engineering basis behind it.

Industrial relay protection panel with overcurrent relays and circuit breakers

Protection Systems Must Isolate Only the Faulted Section — Every Time

IEC 60255  ·  IEC 60909  ·  IEEE 1584-2018  ·  CEA 2023

TL;DR — Key Takeaway

Relay coordination is required because an uncoordinated protection system cannot guarantee that only the faulted section is isolated. Without it, upstream breakers trip first — widening outages, increasing arc flash exposure, and leaving the actual fault uncleared. It is mandated under CEA Safety Regulations 2023 and IEC 60255, and is the engineering foundation for protection system compliance in industrial facilities.

What Is Relay Coordination?

Relay coordination is the process of configuring protective devices — overcurrent relays, circuit breakers, fuses — so each one trips in a defined time sequence during a fault. The device nearest the fault operates first. Upstream devices act only if the downstream device fails to clear the fault within its allotted time window.

Coordination depends on four core properties of any protection system. Selectivity is the most critical. It ensures only the device closest to the fault responds first, isolating the faulted section while the rest of the plant continues to operate.

Most Important

Selectivity

Only the device nearest the fault responds first, isolating that section while healthy parts of the plant remain energised.

Core Property

Speed

Faster fault clearance reduces equipment damage, arc flash energy, and the duration of voltage dips affecting the wider network.

Core Property

Sensitivity

Protection must detect the minimum fault current reliably — including in low-fault-current operating modes such as captive-only generation.

Core Property

Stability

Protection must remain stable under normal load conditions — motor starting currents, transformer inrush — and not operate unnecessarily.

Devices in the coordination chain include overcurrent relays, MCBs, ACBs, VCBs, and fuses. Each has its own time-current characteristic. Coordination aligns these so no two devices compete for the same fault event.


Why Is Relay Coordination Required?

Relay coordination is required because an uncoordinated protection system cannot isolate only the faulted section. It is mandated under CEA Safety Regulations 2023 and IEC 60255, and directly determines arc flash risk levels and nuisance trip behaviour. Without a formal coordination study, protection settings have no verified engineering basis.

When protective devices are not coordinated, a fault in one section causes an upstream breaker to trip before the device nearest the fault. Power is cut to healthy equipment. The fault remains energised. The outage is wider than necessary — and the root cause is still present.

⚠ Consequences of an Uncoordinated Protection System

Upstream breaker trips before the fault device — widening the outage

🔥

Fault remains energised — increasing arc flash exposure duration

🏭

Healthy plant sections lose power unnecessarily — production disruption

🔁

Nuisance tripping on normal load events — motor starting, transformer inrush

📋

No verified engineering basis for protection settings — compliance gap

Extended fault clearance time — higher incident energy per IEEE 1584-2018

Nuisance tripping follows the same failure pattern. Relay settings adjusted during maintenance, without a follow-up study, often result in devices that can no longer discriminate between a transient motor starting current and a sustained fault condition. The outcome is either an unwanted trip on normal load, or a delayed trip on an actual fault.

Fault clearance time — controlled by relay coordination — feeds directly into arc flash incident energy calculations under IEEE 1584-2018. Longer clearance time means higher incident energy at the fault point, increasing risk for personnel working near energised equipment.

"In power system networks, protection must be designed so that protective relays isolate the faulted portion of the network — preventing equipment damage and operator injury, while ensuring minimal system disruption."

SAS Powertech Pvt. Ltd. — Power System Protection Engineering Practice

What Standards Make It a Requirement?

Relay coordination is not discretionary in industrial facilities. Multiple Indian and international standards establish it as a compliance obligation — each covering a different dimension of the requirement.

CEA Safety Regulations 2023 · Reg. 40–41

Indian Statutory Requirement

Protection systems must be maintained in correct working condition, with settings documented and periodically verified. A relay coordination study provides the engineering basis for this obligation.

IEC 60255

Relay Characteristic Curves

Defines IDMT and other relay curves that form the basis of time-current grading in any coordination study. Device settings must conform to these defined characteristics.

IEC 60909

Short-Circuit Current Calculation

Governs fault current calculation — the primary input to relay coordination settings. No coordination study can be credible without a preceding short-circuit analysis per this standard.

IEEE 1584-2018

Arc Flash Incident Energy

Uses fault clearance time — set by relay coordination — as a direct input to arc flash incident energy calculation. Coordination quality directly determines PPE requirements and working boundaries.

IS 18732

Indian Electrical Safety Practices

Covers protection system maintenance obligations for industrial facilities, including requirements for documentation of settings and operational verification.

IEC 60364

Low Voltage Installation Safety

Establishes protection requirements for LV systems, including device coordination as a design requirement for overload and short-circuit protection.

Check where your facility stands in protection system compliance. A professional relay coordination study confirms whether your protection settings reflect current system configuration and meet applicable standards.

Connect with Experts →

How Are Relay Coordination Settings Determined?

Settings are derived from a short-circuit study (per IEC 60909) and time-current characteristic (TCC) analysis. Fault current values at each bus are calculated across all operating modes. Device curves are plotted on a log-log TCC graph, and settings are selected so curves do not overlap — ensuring the downstream device always clears the fault first.

Operating mode matters significantly. In a chemical plant project at Lote MIDC, Maharashtra, the 3-phase fault current at the LT bus varied across three modes. Settings validated at peak fault current behave differently at lower fault levels — particularly in captive-only mode. A credible coordination study accounts for all operating scenarios.

📊 ETAP Field Data — Lote MIDC Chemical Plant, Maharashtra
Operating Mode Source Configuration 3-Phase Fault Current (LT Bus)
Captive Float Mode Grid + DG (parallel) 9.73 kA
Grid-Only Mode Grid supply only 9.05 kA
Captive-Only Mode DG set only 0.98 kA

Source: SAS Powertech ETAP Power System Study — Lote MIDC Chemical Plant. Fault current at the LT bus varies by nearly 10× across operating modes, demonstrating why multi-mode coordination analysis is essential for credible protection settings.

ETAP-based simulation handles this complexity for multi-source, multi-bus systems, modelling IDMT relay curves alongside transformer inrush, motor starting, and equipment damage curves across every mode. The output is a set of verified, mode-specific relay settings with supporting TCC documentation.

ETAP Simulation — What It Produces

One-line diagrams with all protective devices mapped across the distribution network.

Time-current characteristic (TCC) curves for each device, plotted on a log-log graph, confirming non-overlapping coordination bands.

Relay setting tables with pickup current, time dial, and curve type for each overcurrent relay in the coordination chain.

Multi-mode validation confirming settings hold across all operating configurations — grid-only, captive-only, and parallel modes.


When Should a Relay Coordination Study Be Carried Out?

relay coordination study is required at commissioning and must be repeated after any significant system change — new loads, transformer upgrades, DG set additions, or relay setting modifications during maintenance. Recurring nuisance trips or unexplained upstream breaker operations are also clear indicators that existing coordination should be reviewed.

In practice, coordination is rarely revisited after initial commissioning. Equipment is added over time. Settings are adjusted during shutdowns without a formal study. The plant then operates with a protection scheme that no longer reflects its actual system configuration — a condition that is common, often undetected, and typically only identified after a fault event exposes it.

  • At initial commissioning — every new installation requires a baseline coordination study before energisation.
  • After new load additions — additional feeders, motors, or distribution boards alter fault current distribution and may invalidate existing settings.
  • After transformer rating changes or upgrades — transformer impedance directly affects available fault current at every downstream bus.
  • After DG set commissioning or capacity changes — adding a captive source introduces a new fault current contribution that changes coordination requirements throughout the system.
  • After relay setting modifications during maintenance — settings changed without a supporting study are an engineering assumption, not a verified configuration.
  • On recurring nuisance trips or upstream breaker operations — these are symptomatic of a coordination failure and warrant a full review of existing TCC settings.
  • As part of a periodic Electrical Safety Audit — CEA Safety Regulations 2023 require that protection settings be documented and periodically verified.

Frequently Asked Questions

What is the difference between relay coordination and relay testing?
Relay testing verifies that a device operates at its set values. Relay coordination determines what those values should be, based on fault current levels and the time-current characteristics of all connected devices. Coordination must come before testing — the settings need to be correct before they are verified.
What causes nuisance tripping in industrial plants?
Nuisance tripping commonly results from relay settings that were not reviewed after equipment changes or maintenance. When protective devices are not coordinated, a downstream fault can cause an upstream breaker to operate first. Motor starting currents and transformer inrush can also trigger incorrectly set overcurrent relays that have not been calibrated to distinguish between transient overcurrents and sustained fault conditions.
Is relay coordination required under CEA Safety Regulations 2023?
Yes. CEA Safety Regulations 2023 (Regulations 40–41) require that protection system settings be documented and maintained in correct working condition. A relay coordination study provides the engineering basis for those settings and their periodic verification. Without a study, there is no documented engineering justification for the protection values in use.
When should a relay coordination study be repeated?
After any significant equipment change — new loads, transformer additions, DG commissioning, or relay setting modifications during maintenance. Also after any unexplained nuisance trip or upstream breaker operation. Periodic review as part of an Electrical Safety Audit keeps the protection scheme aligned with the current system configuration, as required by CEA Safety Regulations 2023.
How does relay coordination connect to arc flash risk?
Arc flash incident energy — calculated per IEEE 1584-2018 — is directly proportional to fault clearance time. Relay coordination determines how quickly a protective device operates during a fault. A coordination study that minimises clearance time also reduces arc flash incident energy, which in turn determines the required PPE category and working boundaries for personnel near energised equipment.

Get a Professional Assessment of Your Protection System

SAS Powertech conducts independent, ETAP-based relay coordination studies for industrial and commercial facilities across India. Our study reports are structured to serve as technical evidence for CEA compliance and Electrical Safety Audit purposes.

info@saspowertech.com +91-9763003222  /  +91-9011028802 Request a Coordination Study →
About SAS Powertech Pvt. Ltd.

Independent Electrical Safety & Power System Engineering Consultancy

SAS Powertech is an independent electrical safety and power system engineering consultancy with over 25 years of experience across industrial and commercial facilities in India, the Middle East, Southeast Asia, and Africa.

Services include Electrical Safety Audits, Arc Flash Analysis, Relay Coordination Studies, Short Circuit Analysis, Power Quality Audits, Load Flow Analysis (ETAP-based), and Root Cause Electrical Failure Analysis. Each engagement is executed by subject matter experts using ETAP simulation tools and calibrated field instruments.

📧 info@saspowertech.com 📞 +91-9763003222  /  +91-9011028802 📍 01 Gera's Regent Manor, Baner, Pune 411045